Project Overview 

Fort Pitt Grammar School in Rochester had poor teaching facilities in its converted Grade 2 listed Florence Nightingale Hospital Building. The project included the strip out (of non-listed items), significant structural wall alterations and reinforcements, extensive refurbishment and remodelling to provide the following new accommodation: 

  • Reconfiguration of building into Five Classrooms. Including two specialist Music Classrooms and 10 music practice rooms. 
  • Specialist Drama Studio with new lighting and sound rigs, black our blinds and retractable curtains. 
  • Specialist Dance Studio with floor to ceiling mirrors and new rig lighting. 
  • Installation of bi-folding acoustic wall between Drama and Dance Studios. 
  • 2 new external fire escape stair cases. 


The works also comprised the installation of new Variable Refrigerant Flow (VRF) air-source heat pump to provide heating and cooling and installation of Mechanical Ventilation and Heat Recovery (MVHR) units.

  • Location: Rochester, Kent
  • Client: Beyond Schools Trust, Fort Pitt Grammar School
  • Sector: Education
  • Project Duration: 2022 – 2024
  • Services Provided: Coordination of Design Team, Specification Writing, Tender, Project Management and Contract Administration 

 

Our Role / Services Provided 

From initial assessment through to project completion, our team worked closely with the school to provide end-to-end project consultancy services, including: 

  • Initial survey and design options 
  • Leading of full design team to include architect, structural engineer, quantity surveyor, acoustic engineer and planning consultant.  
  • Overseeing planning application submission 
  • Detailed specification writing 
  • Tender issue, evaluation and contractor selection 
  • Contract administration and progress monitoring 
  • On-site inspections and quality assurance reporting 
  • Final snagging and compliance sign-off 

 
Results & Outcomes 

  • School provided with state-of-the-art music, drama and dance accommodation for its students.  
  • Flexible Drama and Dance space provided with acoustic bi-folding wall.  
  • Sustainable VRF system installed reducing carbon footprint from previous cast iron radiators and gas boiler.  
  • Refurbishment and repurposing a historic building.