Case Study: Boiler Replacement, Fire Compliance, Roof Replacement, Heating Distribution and Electrical Rewire at Knaphill School
Project Overview
Knaphill School, located in Woking, required a strategic, multi-year upgrade programme to address significant infrastructure issues across its mechanical, electrical, roofs and fire safety systems. Over the course of three years, our team have delivered a series of planned upgrades to ensure compliance with modern building regulations while improving the building’s safety, efficiency, and long-term sustainability.
- Location: Woking, Surrey
- Client: Knaphill School
- Sector: Education
- Project Duration: April 2022 – December 2024
- Services Provided: Project Management, Specification Writing, Quantity Surveying, CIF Bid Writing, Contract Administration, Compliance Consultancy
Our Role / Services Provided
We provided end-to-end consultancy services across all project phases, including:
- Initial condition surveys and project scoping
- Technical specification development for M&E, Roofs and Fire Compliance
- Tender management and contractor recommendation
- Management of multiple CIF funding applications and approvals
- Construction phase project management and quality assurance
- Contract administration and cost control
- Compliance review and certification sign-off
Scope of Works Completed
Boiler Replacement (2022)
- Decommissioning and removal of life-expired gas-fired boiler plant
- Installation of new high-efficiency condensing boilers
- New plantroom layout including upgraded flue system and controls
- Improved zoning and integration with BMS system
Fire Compliance (2023)
- Replacement of 78 non-compliant internal fire doors with FD30-rated units
- Installation of a new addressable fire alarm system and detectors
- Replacement of 22 non-compliant glazed screens with certified fire-rated glazed units
- Installation of compliant fire exit signage and emergency lighting
- Replacement of 11 external fire exit doors with compliant units including panic ironmongery
Roof Replacement (2023)
- Flat roof replacement including the strip up of existing and installation of a new tapered insulation triple layer built up system, including replacement of rain water goods and down pipes.
Heating Distribution (2024)
- Full replacement of ageing single-fed pipework across all blocks
- Removal of cast-iron radiators and installation of modern steel radiators
- Introduction of thermostatic controls for energy control
- Improved distribution efficiency and occupant comfort
Electrical Rewire (2024)
- Replacement of all electrical distribution boards, submains and final circuits
- New power outlets and general services across all classrooms and administrative areas
- Installation of new LED lighting with improved lux levels and efficiency
Results & Outcomes
- Phased delivery allowed uninterrupted school operations during term time
- Compliance achieved with current Building Regulations and fire safety standards significantly reducing school closure events.
- Significant improvement to teaching and learning environment, thermal comfort, safety, and energy performance
- Enhanced reliability of M&E systems and reduced future maintenance risks
- Positive stakeholder feedback from the substantial works undertaken